Whangārei Heads watermains renewal
- Project typeRenewal
- Project value$2.2M
- Project scheduleNovember 2024 to mid-2025
- Contractor nameNorthern Pipe and Civil Ltd
We are replacing the watermains in Whangārei Heads due to aging and damaged pipes.
The renewals are taking place in three sections along Whangārei Heads Road:
- Section 1 – from Scott Road to The Pines Golf Club (330m) – completed 6 December 2024
- Section 2 – from Pepi Road to Crisp Road (1.9km) – mid-March to late June 2025
- Section 3 – from Bay View Road to approximately 2288 Whangarei Heads Road (1.4km) – 20 January to mid-April 2025.
During the upgrade, traffic management will be in place with stop / go signs and traffic lights where needed.
Residents will be notified by council contractors when there will be disruptions to the water supply (expected during the day only).
Section 1 - From Scott Road to The Pines Golf Club (330m)

Section 1 - Scott Road to The Pines Golf Club(PDF, 347KB)
Section 2 - From Pepi Road to Crisp Road (1.9km)

Section 2 - Pepi Road to Crisp Road(PDF, 399KB)
Section 3 - From Bay View Road to approximately 2288 Whangarei Heads Road (1.4km)

Section 3 - Bay View Road to 2288 Whangarei Heads Road(PDF, 349KB)