Roading improvements
- Project typeRoading
- Project schedule2024 - 2026
Find out about roading improvement projects that have been scheduled, including:
- safety improvements
- new footpaths and cycle paths
- pavement construction
- seal extensions
- resealing
- bridge repairs.
To view roading projects in a map format follow the link below.
Roading improvements and renewal programme GIS map
Our roading projects align with what we say we will do in our Long Term and Annual Plans, and are funded jointly from your property rates and Waka Kotahi.
The 2024 Government Policy Statement (GPS), which covers funding for our roading programme, indicated that no subsidy funding would be made available for council seal-extension projects on local roads for the 2024 - 2027 period.
Also, in our Long Term Plan 2024-2034, we have made no additional budget provision for Council-funded seal-extension projects on local roads. Therefore, no new seal-extension projects are planned on Council roads for the 2024 - 2027 period.
General Circular Investment: No 16 / 04 – Changes to the investment assessment process for the Roading Maintenance and Operations Activity Class (nzta.govt.nz)
View information about the roading recovery and repair process and view a map of the latest repair plans for the land slips caused by severe weather events.
Severe weather road repairs
Below is an overview of the work scheduled within the Roading improvements and renewals programme, grouped by the year the construction is expected to start.
This list was last updated on 10 December 2024.
2024 overview
The following are expected to start construction in 2024.
Location and overview |
Expected start |
Status |
Kamo - Kamo Connections Stage 5B - cycling facilities |
Q1 July - September 2024 |
Complete (physical works) |
Clark Road - Slow streets and footpaths - minor safety improvements |
Q2 October - December 2024 |
Construction underway |
Mangapai Road - Culvert No. 133 - culvert replacement |
Q2 October - December 2024 |
Construction underway |
Marua Road rehab (north) - RP 6940 to RP 7080 = 140m - sealed road pavement rehabilitation |
Q2 October - December 2024 |
Complete (physical works)
|
Maungakaramea Road - RP 8312 - slip repair |
Q2 October - December 2024 |
Complete (physical works) |
Nova Scotia Drive - guard rail - minor safety improvements |
Q2 October - December 2024 |
Construction underway |
Paparoa Road Culvert No. 136 - culvert replacement |
Q2 October - December 2024 |
Construction underway |
Paparoa Road underslip - RP 7820 - retaining structures |
Q2 October - December 2024 |
Construction underway |
Pipiwai Road (north) - RP 1354 to RP 1670 = 316m - sealed road pavement rehabilitation |
Q2 October - December 2024 |
Construction underway |
Pipiwai Road (north) - RP 6030 to RP 6540 = 510m - sealed road pavement rehabilitation |
Q2 October - December 2024 |
Design |
Raumanga South - slow streets (Tauroa Street, Fairburn Street, Hedley Place) - minor safety improvements |
Q2 October - December 2024 |
Construction underway |
Russel Road (north) - RP 15 to RP 383 = 368m - sealed road pavement rehabilitation |
Q2 October - December 2024 |
Complete (physical works) |
Shoemaker Road - RP 4954 - slip repair |
Q2 October - December 2024 |
Complete (physical works) |
Snooks Road (south) - RP 5030 to RP 6380 = 1350m - sealed road pavement rehabilitation |
Q2 October - December 2024 |
Construction underway |
Three Mile Bush Road (south) - RP 3432 to RP 5000 = 1568m - sealed road pavement rehabilitation |
Q2 October - December 2024 |
Construction underway |
Waipu Gorge Road - RP 3741 - slip repair |
Q2 October - December 2024 |
Complete (physical works) |
2025 overview
The following are expected to start construction in 2025.
Location and overview |
Expected start |
Status |
Bay View Road - RP 359 - slip repair |
Q3 January - March 2025 |
Design |
Dave Culham Drive pedestrian crossing - relocate and improvements to zebra crossing - minor safety improvements |
Q3 January - March 2025 |
Procurement (physical works) |
Flyger Road (south) - RP 20 to RP 235 = 215m - sealed road pavement rehabilitation |
Q3 January - March 2025 |
Design |
Gillingham Road - Bridge upgrade - new bridge |
Q3 January - March 2025 |
Design |
Kaiikanui Road - RP 10153 - slip repair |
Q3 January - March 2025 |
Design |
Pātaua North Road overslip - RP 11810 - retaining structures |
Q3 January - March 2025 |
Planning |
Raumanga Shared Path Stage 4 - extension to Te Mai Road and lighting |
Q3 January - March 2025 |
Design |
Raumanga Valley Road (south) - RP 145 to RP 540 = 395m - sealed road pavement rehabilitation |
Q3 January - March 2025 |
Design |
SH1 and Springsflat - new roundabout |
Q3 January - March 2025 |
Design |
Snooks Road - RP 7240 - slip repair |
Q3 January - March 2025 |
Design
|
Tatton Road (north) - RP 1465 to RP 2000 = 535m - sealed road pavement rehabilitation |
Q3 January - March 2025 |
Design |
Crows Nest Road - RP 6372 - slip repair |
Q4 April - June 2025 |
Design |
Gray Road - RP 25 - 1325 (1.3km) - seal extension
|
Q4 April - June 2025 |
Design |
Karaka Road - RP 4990 - slip repair |
Q4 April - June 2025 |
Design |
Kauri Mountain Road - RP 1677 - slip repair |
Q4 April - June 2025 |
Design |
Ngunguru Footpaths - new footpath (linking playground, sports park etc.) |
Q4 April - June 2025 |
Planning |
Nova Scotia Drive - Bridge No. 102 - pile jacketing - structure component replacement |
Q4 April - June 2025 |
Design |
Royden Road (north) - RP 120 to RP 380 = 260m - sealed road pavement rehabilitation |
Q4 April - June 2025 |
Design |
Waipu Caves Road - Bridge No. 106b - beam repair / replacement - structure component replacement |
Q4 April - June 2025 |
Design |
Ormandy Road , RP 4791 - 6791 (2.0km) - seal extension |
Q2 October - December 2025 |
Design |
2026 overview
The following are expected to start construction in 2026.
Location and overview |
Expected start |
Status |
Mclean Road, RP 400 - 1910 (1.5km) - seal extension |
Q4 April - June 2026 |
Design |
To be confirmed
The construction start dates for the following are to be confirmed.
Location and overview |
Expected start |
Status |
Kamo Rail Overbridge (design only) - structure component replacement
|
N/A - Design only |
Design |
Ngunguru Road and Maruata Road - land purchase - right turn bay |
N/A - Design only |
Design |
Reyburn Street Bridge - Design only - structure component replacement |
N/A - Design only |
Design |
Whareora Road (south) - RP 390 - 1080 = 690m |
N/A - Design only |
Planning |
Ngunguru Road - signage - minor safety improvements |
|
Complete (physical works) |
White Road - bridges and structures renewals |
|
Complete (physical works) |
Expected start dates (each year)
- Q1: July - September
- Q2: October - December
- Q3: January - March
- Q4: April - June