Dave Culham Drive road safety improvements

  • Project typeSafety improvements
  • Project value$430,000
  • Project schedule6 to 31 January 2025
  • Contractor nameWM Construction
  • Completion Date31 January 2025
An image of Dave Culham Drive showing where improvement works will take place.

We relocated the existing pedestrian crossing on Dave Culham Drive.

We installed the pedestrian crossing to comply with new best-practice requirements outlined by Waka Kotahi.

This crossing forms an important link for future cycleways and shared paths. It creates a safe crossing to the Pohe Island Bike Park, Pohe Island Pump Park and the Whangārei BMX Club.

What we did

  • relocated the existing pedestrian crossing
  • extended the road median and installed a new island
  • installed some new kerb and channel to improve drainage
  • increased street lighting.   

Location

Dave Culham Drive, Whangārei 0112  View Map