Foundations
|
Excavation for foundations (piles, posts, etc)
|
This is the first inspection generally for a timber floored building – it is a check of the building position and orientation on the site, of the ground conditions, and the position and depths of timber pile / post footings.
|
Excavation and reinforcing in foundations
|
This is for a concrete floored building – it is a check of the building position and orientation on the site, of the ground conditions, and the position and depths of foundations and the reinforcing content.
|
Under floor slab plumbing
|
A check of the drainage system beneath the slab – a check of the layout, materials used, falls, observation of the drainage system ‘on test’ – i.e. holding water.
|
Slab on ground prior to pouring concrete
|
A check of the slab, prepared for pouring concrete – a check of slab thickness, damp proof membrane and blinding material and reinforcing steel.
|
Foundation wall reinforcing
|
A check of the laying of the blockwork or construction of the formwork for the wall, reinforcing content, washout points to blockwork.
|
Waterproofing of retaining walls prior to backfill
|
A visual check of the membrane applied to the exterior of a retaining wall, extent of the membrane, protective blinding, drainage behind wall, suitability of fill material (free draining).
|
Other reinforcing steel as required
|
A check of any other reinforcing steel in a project not related to any of the previous inspections before concrete is poured – i.e. intermediate floors, masonry block walls, columns, beams, etc.
|
Timber Sub Floor
|
Timber sub floor prior to flooring being fixed
|
A check of the subfloor structure, subfloor structural connections, timber treatment, bearers, subfloor braces, prior to laying of flooring to permit easy visual inspection.
|
Framing
|
Fixings pre roofing and pre wrap
|
A comprehensive check of the assembly of the structural skeleton of the building – wall and roof framing, prior to fixing of wraps and claddings. A thorough check of framework and structural connections is carried out along with checks of external bracing elements (typically plywood sheets).
|
Direct fixed post wrap / flashing / cladding fixings
|
A check of the cladding and window installation during the cladding process for direct fixed claddings. At a minimum, a visual inspection of the installation of one window and the adjacent cladding to demonstrate that the flashing and cladding systems will meet the requirements of the manufacturers literature and the Building Code. A check of the roofing installation will generally be carried out at this stage concurrently.
|
Cladding
|
Brick veneer check (first day / half height)
|
A check of the brick veneer under construction, a check of the laying of the brickwork, brick cavity width, brick ties, and of the condition of the wall wrap, etc.
|
Cavity battens
|
A check of the cavity battens, over the building wrap, prior to the fixing of the cladding. Batten position, vermin proofing, window installation and securing of wall wrap are checked. A check of the roofing installation will generally be carried out at this stage concurrently.
|
Pre-plaster
|
A check of the plaster substrate prior to applying any plaster coating.
|
Pre Line
|
Pre-lining including moisture content and plumbing under pressure
|
A check of the internal space of the building, before fixing of wall linings. Inspection includes a framing moisture content check, check of insulation installation, hot and cold water supply pipework, structural framework fixings required for wall bracing panels, and a check of the completed cladding installation and the weathertightness of the external envelope.
|
Post line
|
Fire separation wall during lining
|
Check of fire walls prior to lining – check of framing, structural fixings, penetrations and similar considerations.
|
All bracing panels
|
A check of internal wall bracing panels (typically plasterboard) and their fixings to the framing prior to being gib stopped. Position, length and type of wall brace will be checked against the consented design.
|
Drainage
|
Drainage before any work is covered up including test, and including connection inspection if using Council system
|
A check of the sanitary and storm water drainage systems and effluent disposal systems prior to backfilling trenches. A check of the layout, materials used, falls, observation of the drainage system ‘on test’ – i.e. holding water. A Drainage As-Built Plan is required to be submitted to Council by the drain layer at this stage.
|
Final
|
Final - when all work covered by the consent is completed
|
The last inspection of the building project. Final collection of paperwork – Producer Statements, Memoranda, As-Built plans, Electrical and Gas Certificates, Code Compliance Certificate Application form.
On residential projects, It is also check of any outstanding items raised at previous inspections, hot water supply temperature check, and a check of final finishing items – bathrooms, kitchens, laundries, landscaping, driveways, smoke alarms etc.
On commercial projects, access routes and facilities for persons with disabilities, carparks, emergency exits, signage and emergency lighting, water supply temperature check, etc.
|
Fireplace inspections
|
Free standing - after installation of heater but prior to installation of flue ceiling plate
Inbuilt - when fireplace is prepared but prior to installation of heater
|
Swimming Pool inspections
|
Excavation prior to installation: in ground pools, prior to concreting or installing fibre glass insert.
Fencing and backflow device: check of fencing and barriers complying with the Fencing of Swimming Pools Act 1987, and backflow prevention device fitted to nearest hose tap to pool.
|